PROCESS OUTLINE

SETTLEMENT OF LAND

Pre Project Or 1-2 Months

Usually land is already purchased before this process. For larger developments this process happens as a part of the raise.

DEMOLITION PROCESS

2-4 Weeks, Any Phase Before Construction

Clearing of debris or previous constructions.

DA APPROVAL IF REQUIRED

3-6 Months

The DA Process can extend if council and local approvers require different designs and additional scope of works.

DESIGN AND CONSULT

3-4 Months

The Design and consult process is a final design process that enablesĀ  us to get the maximum allowable on sites as well as engages multiple consultants on fire, engineering, structural, gas energy, traffic, sound.

BUILDING APPROVAL PROCESS

3-6 Months

Building Approval is submitting final DA approved (if necessary) designs to council in order to begin construction process. This process can be extended if the council require drawings or additional items added to the development to ensure it complies with council guidelines.

CIVIL / EARTHWORKS

Up to 2 Months

All pre process pertaining to the preparation of the land and civil services.

CONSTRUCTION PROCESS

Up to 14 Months

Physical construction of the property.